Nova Chip

The City of Sunset Hills Public Works Department will be applying a Nova Chip to Deane, Monica, Floralea, Lynstone, Windward Ridge, Homecrest, Tolstoi, and Spears in 2017. 

Nova Chip is a product the City has used successfully on numerous asphalt pavements, including West Watson from I-270 to Rott Road by the old Rott School, then on Rott Road from Pickle Hill to S. Lindbergh, including the entrance to the rear of Sunset Plaza, among other streets throughout the City.

2017 Nova Chip
A Nova Chip is a type of asphalt, typically more porous, but has a different application of the bonding agent that is immediately before the placement of the material. You can drive on it almost immediately after rolling it out. You'll note this material used by MoDOT on I-44 and I-270, north of I-44.
Photos
Here are some pictures of the process as applied in 2010 to Lombardy Lane in Sunset Hills:

Paving machine spreads the material evenly.

Paving machine

Rolling the material falls right in behind placement by the paver

Rolling the material falls right in behind placement by the paver

Hand work right along side the rolling operation

Hand work right alongside the rolling operation

Finished product is almost immediately ready for traffic

Finished product

Project Updates


  • April 19, 2017 - City Staff were in the field measuring and assembling notes to put together a bid package for this project.  A copy of the bid package is available here.
  • April 20, 2017 - A bid package was prepared for this work.  This bid package was solicited to known contractors and the newspapers for bid consideration. 
  • May 2, 2017 - A Pre-Bid meeting was scheduled.  No one attended.
  • May 3, 2017 - Bids were received. The results were:
  •  Place Contractor   Grind & 
    Nova Chip/SY
    Lump Sum 
    26,397 SY 
     1 NB West $7.30  $192,698.10
  • PACE thought the bid was due at 11:00am, apparently mistaking the time of 11:00am for yesterday's Pre-bid.  The City could not accept this bid after 10:00am.
  • May 4, 2017 - Results could not be presented to the Public Works Committee as they lacked a quorum to conduct business.
  • May 9, 2017 - Results of the bid were presented to the Board of Aldermen and the project was awarded to NB West Contracting.
  • May 16, 2017 - A Notice of Award was processed and sent to NB West. The responded with a note saying the expect to begin work in early to mid June. The project should take only be five or six days total.  They expect to be able to finish by the end of June.  Optimistically they could start as early as June 5th or 6th.
  • May 22, 2017 - Contracts have been prepared. NB West is acquiring Payment & Performance Bonds.
  • May 23, 2017 - Contracts were executed and project signs were placed in the field to advertise to the public this morning.
Anticipated Events
  • June 2, 2017 - A Pre-Construction Meeting will have been held. The contractor will advise of further details of their schedule for this work.  The work can commence.
  • June 30, 2017 - The work will be complete with daily updates provided on the project listed on this web page.