City Campus Parking Rehabilitation

The City of Sunset Hills will be replacing perimeter asphalt curbing with concrete curb & gutter, removing the asphalt pavement and replacing same with new asphalt paving on the City Campus. 

This project is anticipated to be completed in phases with the City Hall and Community Center parking areas replaced in 2019.  It is hoped the remainder (Public Works Garage & Police Facility) with associated connecting roads will be completed in 2020.

This page will follow the format of the other City Project pages with project plan preparation, a PDF of the bid package, bidding tabulations, review/award information, and daily updates of progress as the project gets underway.

PROJECT UPDATE

Contractor Bid Repair Soft Soil
Jokerst $217,891.67 $65.00 / Ton
Spencer
$249,895.25 $37.50 / Ton
Ford Asphalt $260,074.45 $50.00 / Ton
Leritz $339,360.79 $112.40 / Ton

  • 6-6-19 - Jokerst just called and plans to start cutting tomorrow.  They will start out in behind City hall in the Public Works Staff car area, move out to the 4 car parking area and then to the City Hall parking on the side closest to S. Lindbergh.  Staff placed cones in the areas to keep these open to Jokerst for this work.  They will not be removing the old curb tomorrow, just cutting the existing asphalt in preparation for removal and placement of the new concrete curb & gutter. 
  • 6-7-19 - Jokerst is onsite cutting asphalt in preparation for placement of the new concrete curbing. 
  • 6-10-19 - The Public Works Department is digging out the rear of City Hall to place a drain in this area for the guttering. 
  • 6-11-19 - The Public Works Department is placing a drain in at the rear of City Hall to relieve the guttering.
  • 6-12-19 - The Public Works Department is finishing up the drain placement to the rear of City Hall.  Jokerst called and plans to start digging in the large parking lot tomorrow where they cut out the pavement last week.  Bucheit plans to be on-site Tuesday (June 18th) to start placement of the new concrete curb.
  • 6-13-19 Jokerst is onsite and starting curb removal on the large parking lot.  They provided a sequence to their work.  The colored area on the map below will roughly follow the sequence listed in the key.
Parking Project Staging
  • 6-13-19 Jokerst is onsite and starting curb removal behind City Hall.
  • 6-17-19 - Bucheit is onsite and starting curb form placement in the Yellow area.


2019 Parking