Trench Drain Repair





SEE BOTTOM OF PAGE FOR UPDATES

Location Map

Trench Drains

BID ANNOUNCEMENT

Storm Water Inlet Trench Drain 2022

 

            The City of Sunset Hills Public Works Department is soliciting bids for replacement of 2 storm water inlet channels.  Once channel is on at 11052 Triple Oaks, Sunset Hills Mo 63127 and the other is at 9420 Sunny Creek, Sunset Hills MO 63127.   Removal and replacement of the complete storm water inlet channels. Sealed bids will be received until 10:00am; Wednesday, March 31, 2022. 

 

            There will be no pre-bid meeting for this project. Bidders interested call Jerry Eime at 314-488-4264 if question or meeting is needed.

 

            Specifications are available at the Drexel Plan Room at https://planroom.drexeltech.com/View/Default.aspx   

 

Bids will be reviewed and the one deemed in the best interest of the City of Sunset Hills will be recommended to the Sunset Hills Board of Alderman for approval at their June 14, 2022 meeting.  The City reserves the right to reject any or all of the bids, to waive technicalities, to award on any bid that is most advantageous and to make investigations concerning the experience and ability of the bidder to perform the work.

 

            The City of Sunset Hills does not discriminate against any company or individual on the basis of race, religion, creed, color, sex, physical disability or national origin.

 

            Questions regarding the bid should be submitted to Jerry Eime, Street Superintendent at 314-272-2458 or jeime@sunset-hills.com

            

            The City reserves the right to reject any or all bids, waive technicalities, to award on any bid that is most advantageous and to investigate the experience and ability of the bidder to perform the work. Bids should be accompanied by a bid surety in the form of a certified check or bid bond for 5% of the bid total.  More details concerning this work is available at www.sunset-hills.com  

 

Jerry Eime

Street Superintendent

314-272-2458

Description: Description: sunset

UPDATES

  • 3-31-22 - Bids were received for this project at 10am.  The following are the results:
Bid Order
Contractor
Total
Extra Rock
1
Jokerst
$56,000.00
$40.00 / Ton
2
Aztec
$70,769.00
$175.00 / Ton
3
Kozeny-Wagner
$80,750.00
$50.00 / Ton


  • 4-7-22 - The Public Works Committee recommended the bid by Jokerst to  the Board of Aldermen for approval.
  • 4-26-22 - The Board of Aldermen award this project to Jokerst.
  • 4-27-22 - A Notice of Award was be sent.
  • 11-1-22 - Project Start is anticipated on this Thursday, November 3, 2022.  Jokerst scheduled a Pre-construction meeting with staff for tomorrow at 1pm.
  • 11-2-22 - From the Pre-construction meeting, it was determined that with the weather forecast, Jokerst plans to start on Monday at Triple Oaks.  They plan to remove one side at a time, but will supply plates to open both lanes outside of work hours.
  • 11-7-22 - Jokerst is on-site and removing the trench drain on Triple Oaks Drive.
  • 11-8-22 - Jokerst continues with removal of the trench drain on Triple Oaks.
  • 11-9-22 - Jokerst is building forms for the new trench drain walls.
  • 11-10-22 - Jokerst continues with forms for the new trench drain walls.  They hope to pour the walls tomorrow.
  • 11-11-22 - Jokerst had more wall forms to work on at Triple Oaks Drive.  they now plan to pour the walls for this trench drain on Monday.
  • 11-14-22 - Jokerst plans to pour the Triple Oaks trench drain tomorrow.
  • 11-15-22 - Jokerst poured the Triple Oaks trench drain today.
  • 11-16-22 - Jokerst is ripping out inbound lane slabs to prepare for pour back of this area that ties into the new trench drain on Triple Oak.
  • 11-17-22 - Jokerst will be starting on Sunny Creek with removal of the trench drain today.
  • 11-21-22 - Jokerst is forming the outbound half of Sunny Creek today.
  • 11-22-22 - Jokerst continues forming  the outbound half of Sunny Creek.
  • 11-23-22 - Jokerst poured the first half of Sunny Creek today.
  • 11-28-22 - Jokerst is removing forms from the first half of Sunny Creek.
  • 11-29-22 - Jokerst is  preparing the inbound side of Sunny Creek today.
  • 11-30-22 - Jokerst continues to prepare the inbound side of Sunny Creek.
  • 12-1-22 - Jokerst is pouring the inbound side of Sunny Creek.
  • 12-2-22 - Jokerst is preparing the outbound slabs of Triple Oak today.  This area was poured later in the day.

ANTICIPATED EVENTS

  • 11-23-22 - Project Completion.